I have 4 200 watt panels, the specs are:
Max Operating Voltage (Vmpp): 21.01Volts
Max Operating Current (Imp): 9.52Amps
Open Circuit Voltage (Voc): 24.29Volts
Short Circuit Current (Isc): 9.89 Amps
I want to charge 2 100ah Battle Born batteries in 24 volt config.
I have Victron MPPT 100/30 Controller
Might I overload the controller if I wire them all in series? Or,
If I S2, P2 will I have enough volts?