PNW_Solar_Guy
New Member
- Joined
- Mar 31, 2022
- Messages
- 25
Hey everybody,
Well I signed up on DIY Solar Forum last year, which was when I did the bulk of the work on out off-grid system as far as purchasing and building goes.
Now I'm at the point where I need to pull my wires, get everything wired up and turn the system on. I'm a little stumped though on where I need to install fuses, disconnects or any other shutoffs. I'd like to run some points past some more experienced DIYers, as I'm definitely not that, this being my very first solar system.
Here is a sketch of the system and plan as an overview.

Here is what I've got done so far.
I bought 2 pallets of 460w bi-facial BluSun panels, 70 panels in total. Designed and had fabricated adjustable racking, and I have 2 of those fully set up with panels mounted, which you can see in these photos.


We decided to pour concrete below each array to meet wind load needs with the added benefit of light reflection onto the backs of the panels, and no need for mowing or weed abatement under and around the arrays.

Each array is 16 panels, two separate 8-panel strings in series (the two strings on each array are not paralleled). I don't have photos included here but you can sort of see where I trenched and laid conduit stubbed up through the concrete on each array pad. All 1" conduit then comes up behind the 2nd array, between the forest and the backside of that array (you can see the grouping of pipes in a few of the photos).

We rented a trenching machine and trenched 300' through the forest. I have 300' of 1 1/2" conduit as well as a separate 1" conduit (for future expansion of the system if needed). Those conduit stub up next to the solar shed that we built on the other side of the 300' of trees, shown here.

Our well head for this field is just out of the frame of this photo. The pressure tank for this well is also going inside the solar shed, and pipes were trenched and set as shown here, before the concrete pour. Those are the water line pipes going to the various outbuildings and garden areas.

Here's the same shot now with the pad poured. I buried two parallel 2" conduits with sweeps. My plan is to run my lines from the inverters through those, under the slab, and up into the load panels on the opposite wall (nearest the camera).

Completed. This shot also shows the well head there next to the pressure tank.

Here is the back side of the solar shed, which shows the trench and the two conduit pipes stubbing up just exterior to the solar shed. The wires from all 6 arrays will enter the backside of the solar shed there, right in the middle.
Here is a sketched plan for what I plan to mount on the backside wall of the solar shed (where the PV wires all enter from the forest trench).

I see that I'm only allowed to attach 10 photos to this post, so I'll leave out the photos of the interior of the solar shed for now.
The inverters will go inside the shed as shown in the sketch above. I bought (4) EG4 6500-EX inverters, with the plan to get 4 more eventually (again, as shown). I will be adding server rack batteries to the system. For now I own (5) Pytes 48v 5.12kwh LiFePo batteries, will likely be adding Signature Solar batteries going forward.
Signature solar also shipped (4) IMO DC Disconnect Rooftop Isolator Switch, as well as (4) Nader DC Circuit Breaker | 60V 200Amp.
I'd love to hear any feedback in general on the system. I'm also happy to answer any questions if anyone has them.
I am about to pull all of the wires (10AWG) from the arrays to the solar shed, probably in the next 1-2 weeks.
For anyone who knows their stuff, I'd love to hear your thoughts on these questions I have about what's left for my system:
Let me know if any questions or more photos needed. Like I said, I was only able to attach 10 to this post, so I can post below this if needed.
Well I signed up on DIY Solar Forum last year, which was when I did the bulk of the work on out off-grid system as far as purchasing and building goes.
Now I'm at the point where I need to pull my wires, get everything wired up and turn the system on. I'm a little stumped though on where I need to install fuses, disconnects or any other shutoffs. I'd like to run some points past some more experienced DIYers, as I'm definitely not that, this being my very first solar system.
Here is a sketch of the system and plan as an overview.

Here is what I've got done so far.
I bought 2 pallets of 460w bi-facial BluSun panels, 70 panels in total. Designed and had fabricated adjustable racking, and I have 2 of those fully set up with panels mounted, which you can see in these photos.


We decided to pour concrete below each array to meet wind load needs with the added benefit of light reflection onto the backs of the panels, and no need for mowing or weed abatement under and around the arrays.

Each array is 16 panels, two separate 8-panel strings in series (the two strings on each array are not paralleled). I don't have photos included here but you can sort of see where I trenched and laid conduit stubbed up through the concrete on each array pad. All 1" conduit then comes up behind the 2nd array, between the forest and the backside of that array (you can see the grouping of pipes in a few of the photos).

We rented a trenching machine and trenched 300' through the forest. I have 300' of 1 1/2" conduit as well as a separate 1" conduit (for future expansion of the system if needed). Those conduit stub up next to the solar shed that we built on the other side of the 300' of trees, shown here.

Our well head for this field is just out of the frame of this photo. The pressure tank for this well is also going inside the solar shed, and pipes were trenched and set as shown here, before the concrete pour. Those are the water line pipes going to the various outbuildings and garden areas.

Here's the same shot now with the pad poured. I buried two parallel 2" conduits with sweeps. My plan is to run my lines from the inverters through those, under the slab, and up into the load panels on the opposite wall (nearest the camera).

Completed. This shot also shows the well head there next to the pressure tank.

Here is the back side of the solar shed, which shows the trench and the two conduit pipes stubbing up just exterior to the solar shed. The wires from all 6 arrays will enter the backside of the solar shed there, right in the middle.
Here is a sketched plan for what I plan to mount on the backside wall of the solar shed (where the PV wires all enter from the forest trench).

I see that I'm only allowed to attach 10 photos to this post, so I'll leave out the photos of the interior of the solar shed for now.
The inverters will go inside the shed as shown in the sketch above. I bought (4) EG4 6500-EX inverters, with the plan to get 4 more eventually (again, as shown). I will be adding server rack batteries to the system. For now I own (5) Pytes 48v 5.12kwh LiFePo batteries, will likely be adding Signature Solar batteries going forward.
Signature solar also shipped (4) IMO DC Disconnect Rooftop Isolator Switch, as well as (4) Nader DC Circuit Breaker | 60V 200Amp.
I'd love to hear any feedback in general on the system. I'm also happy to answer any questions if anyone has them.
I am about to pull all of the wires (10AWG) from the arrays to the solar shed, probably in the next 1-2 weeks.
For anyone who knows their stuff, I'd love to hear your thoughts on these questions I have about what's left for my system:
- QUESTION #1: I plan to bring all 12 pairs of red/black 10AWG wires into a large weatherproof box at the back of the arrays, where my conduits all stub up. This will be for system shutoffs (perhaps the IMO DC disconnects here), one for each of the 6 arrays. Then the wires will all go into the 1 1/2" conduit through the forest and into the solar shed. My question here is, are DC disconnects required there by the arrays, or just a good idea (in case of emergency, so you can shut them off right there and then)? If required, should I use the IMO disconnects, or some other kind of DC disconnects?
- QUESTION #2: Is a DC disconnect also required on the outside of the solar shed, before the wires enter that building? This seems redundant, but I seem to remember someone saying NEC code requiring this as well?
- QUESTION #3: Does code require me to ground all of my arrays? If so, what do they need to be grounded to? I do have a ufer buried next to my solar shed, but I would prefer not to run a grounding wire that full 300' to the solar shed for that.
- QUESTION #4: What fuses and disconnects do I need to purchase (if any, aside from the 4 200A Nader DC circuit breakers) for my inverter and battery setup inside of the solar shed? My aim is to make that inverter wall very clean with no exposed wires, by using metal pipe underneath each inverter routed right into a long wireway. This is the part I have the most questions on so I'm hoping to get some help on that solar shed wall setup.
Let me know if any questions or more photos needed. Like I said, I was only able to attach 10 to this post, so I can post below this if needed.