JonahJimson
New Member
Hi everyone,
First off, sorry if this is in the wrong section. I've been dealing with a huge headache lately and don't know how to proceed.
I hired a company to install a grid-tied 12 kW roof mounted system (Luxpower 12k, 11 kW of PV and 2 x pytes 5.12 kWh). We applied for net metering but was rejected due to no capacity, and I was told that I can still interconnect the system and use the bypass feature of the Luxpower to draw from grid whenever solar or battery is sufficient. So then the install is done, and the times comes to have the system inspected. Inspection passes no problem, but then the inspector sends a notice to the power company that the install passes code, and then all of a sudden PoCo comes out and locks my system, tells me they don't allow interconnections due to my area being restricted. I tried to tell them I have a battery system and will be using the generated energy to cover my loads in a separate subpanel, to which they respond that even if no energy is exported, the fact that I'm using my own energy when the grid is available, it produces an imbalance in their distribution lines and they won't allow it.
I tried to find what what they're referencing and I think this is it:
"The following rules must be followed for these backup generators:
So basically, I'm only allowed to use my system when the grid is out, which means my system right now and almost all of the time will be pretty much a glorified $40k brick. Is there anyway to change the wiring layout to go around this? Installer is of no help and keeps saying we're working on it. I found a document where it talks about a "break before make switch". I've attached it here, would it be possible to go around this restriction using that kind of switch?
First off, sorry if this is in the wrong section. I've been dealing with a huge headache lately and don't know how to proceed.
I hired a company to install a grid-tied 12 kW roof mounted system (Luxpower 12k, 11 kW of PV and 2 x pytes 5.12 kWh). We applied for net metering but was rejected due to no capacity, and I was told that I can still interconnect the system and use the bypass feature of the Luxpower to draw from grid whenever solar or battery is sufficient. So then the install is done, and the times comes to have the system inspected. Inspection passes no problem, but then the inspector sends a notice to the power company that the install passes code, and then all of a sudden PoCo comes out and locks my system, tells me they don't allow interconnections due to my area being restricted. I tried to tell them I have a battery system and will be using the generated energy to cover my loads in a separate subpanel, to which they respond that even if no energy is exported, the fact that I'm using my own energy when the grid is available, it produces an imbalance in their distribution lines and they won't allow it.
I tried to find what what they're referencing and I think this is it:
"The following rules must be followed for these backup generators:
- Backup generation cannot be used to displace load at any time when regular utility supply is available.
- Portable backup generators may be used without the use of a transfer device, provided there is no possibility to inject power into the grid.
- Permanently installed backup generators must have an open transition transfer switch to ensure backup generator is never parallel to the distribution grid."
So basically, I'm only allowed to use my system when the grid is out, which means my system right now and almost all of the time will be pretty much a glorified $40k brick. Is there anyway to change the wiring layout to go around this? Installer is of no help and keeps saying we're working on it. I found a document where it talks about a "break before make switch". I've attached it here, would it be possible to go around this restriction using that kind of switch?