For sake of discussion, lets say 6 (40VOC 10A) panels in 3S2P (for a VOC ~120V)
Where should the inline fuses go? I assume I can wire each into series, branch connect, then fuse after the connector for ~25A?
Upon more research, it looks like the panels I have a short of 10.4A, and Max series fuse rating of 20A, meaning when I go into parallel, they would infact (barely) exceed 20 (20.8 vs 20), thus an inline fuse is needed on each line?
Where should the inline fuses go? I assume I can wire each into series, branch connect, then fuse after the connector for ~25A?
Upon more research, it looks like the panels I have a short of 10.4A, and Max series fuse rating of 20A, meaning when I go into parallel, they would infact (barely) exceed 20 (20.8 vs 20), thus an inline fuse is needed on each line?
Last edited: