The only T- Fuses I could get hands on are the go-power 300 amp., and that took 4 vendors to get
also got the smart shunt
batteries EG4 x 6
should I be using 4/0 battery cables for the entire system ? or is smaller size OK from inverters to buss, fuses are 300 amps
also I did reverse the negative buss bar in the battery rack, as some folks mentioned. this will make both battery wires about 3 ft longer, is it worth it ?
The idea is to keep pos/neg cables exact same length, correct ?
anything else Im getting wrong or suggestions ?
will be extending the 6x6 wireway 2 ft to the left under the transfer switch which I added after seeing some of the installs folks on this website have done.
Have 2 midnight solar 30 amp breakers for each array, 2 strings paralled on each inverter
a/c panel is 125 amp using 60 amp breaker
l
also got the smart shunt
batteries EG4 x 6
should I be using 4/0 battery cables for the entire system ? or is smaller size OK from inverters to buss, fuses are 300 amps
also I did reverse the negative buss bar in the battery rack, as some folks mentioned. this will make both battery wires about 3 ft longer, is it worth it ?
The idea is to keep pos/neg cables exact same length, correct ?
anything else Im getting wrong or suggestions ?
will be extending the 6x6 wireway 2 ft to the left under the transfer switch which I added after seeing some of the installs folks on this website have done.
Have 2 midnight solar 30 amp breakers for each array, 2 strings paralled on each inverter
a/c panel is 125 amp using 60 amp breaker
l