kyleStriker33
New Member
Have been using this old 125a panel with 2 AC units, 11kw of ac coupled solar and 2 tesla home chargers (set for peak 48a draw between the two and only charge at night). It is obviously an original panel and was installed in late 80s but the config mentioned above was mostly in place 5 years ago except for the 2nd EV charger and that was likely the straw that broke this old panel's back (but even that lasted 10 months). My mistake was not replacing the panel at the time we added the solar. Technically it wasn't needed per code but that would likely have avoided this issue. Noticed an odd smell in the garage (panel is external but shares a wall with garage) and thought it was a water leak (smelled like wet drywall to me). Days later some lights were flickering and immediately checked panel. woops...

Started the process for sdge to approve a panel upgrade (emergency fast track not allowed with an upgrade). My electrician took out the failed breaker and sanded the mutilated bus bars and replaced with a new 100a main breaker. We stopped using big loads like, ev and electric oven but it wasn't enough and that new breaker failed again in 1 week.

So my electrician had to bypass those bus bars at that spot, combine some loads and we have been good for 8 weeks now.

By the way it's been 11 weeks and no approval yet from sdge. I did see a contract electrician for them roll up to open my panel and the underground feeder box about 3 weeks ago.

Started the process for sdge to approve a panel upgrade (emergency fast track not allowed with an upgrade). My electrician took out the failed breaker and sanded the mutilated bus bars and replaced with a new 100a main breaker. We stopped using big loads like, ev and electric oven but it wasn't enough and that new breaker failed again in 1 week.

So my electrician had to bypass those bus bars at that spot, combine some loads and we have been good for 8 weeks now.

By the way it's been 11 weeks and no approval yet from sdge. I did see a contract electrician for them roll up to open my panel and the underground feeder box about 3 weeks ago.