chrisjx
New Member
Describing the system we installed. Would appreciate any feedback on where we might have gone terribly wrong. The system is turned off for now until I can get back and spend some time monitoring and tuning.
Summary by Chris Jefferies.
The primary design objective is to support an off-grid residence with a daily energy demand of approximately 60 kWh. A seasonally adjustable ground-mounted array paired with LiFePO4 battery storage and advanced inverter synchronization provides a scalable and resilient energy solution.
Site Characteristics:
The following day at 10:30 AM, system monitoring showed:
Wednesday: The ground mount was framed up and 2 test panels mounted.
Thursday: The 56 panels were mounted to the frame.
By Sunday eve, the batteries were installed in racks, the inverters were mounted on the walls and the cables were set in place for routing and sizing.
During the course of the second week: people were traveling. We purchased overlooked and locally sourced items such as a junction box for the PV wire terminations at the array, PVC pipe (and associated breakers), the AC load box, and the Container/Carport panel.
Saturday: The trenches were dug, cables were bundled.
Sunday: The cables were pulled into PVC, and the trenches were covered.
Monday: The PV wires were terminated, 32 in the PV junction box and 16 into the 4 inverters. The AC Load box was also mounted and wired from each inverter. And finally, the container panel ,meant for provisioning power to the container and other devices in the carport, was wired from the load box. By 6PM we had all systems wired and checked. We powered up the batteries, the inverters and saw 51.1 VDC on each inverter's battery input. We could also see about 320 VDC coming in from the 8 PV strings. However we could not see any voltage on the AC output load side.
After dinner we went out to debug what seemed to be a software configuration problem. By midnight we found the issue to be that we were to plug the master inverter to master battery connection into the CAN bus socket. We plugged a lamp into the Container box outlet and achieved what we called, first-light.
System Completion Highlights:
System Report: 56-Panel Solar Energy System – Brenham, TX
Summary by Chris Jefferies.
1. Summary
This report presents a comprehensive technical overview of a custom-designed 56-panel, 48V off-grid solar energy system located in Brenham, Texas. The system was engineered and implemented over a two-week construction period by a dedicated volunteer team. It features high-efficiency photovoltaic generation, robust energy storage, and future-ready AC load distribution infrastructure.The primary design objective is to support an off-grid residence with a daily energy demand of approximately 60 kWh. A seasonally adjustable ground-mounted array paired with LiFePO4 battery storage and advanced inverter synchronization provides a scalable and resilient energy solution.
Site Characteristics:
- Location: Brenham, TX
- GPS: ...
- Soil Type: Dense central Texas clay
- Climate Reference: WeatherSpark Solar Data – Brenham
- Solar irradiance: ~6.5 kWh/m²/day in summer; ~4.5 kWh/m²/day in winter
- Wind: Moderate, 7–10 mph
- Panel orientation: Optimized with 15° summer and 45° winter tilt
2. System Components and Configuration
2.1 Solar Array and DC Circuitry
- Mounting System: Sinclair Designs Sky Rack 2.0
- Tilt range: 15° (summer) to 45° (winter)
- Six 2' diameter, 7' deep concrete footings with 4000 psi concrete
- Photovoltaic Panels: 56x REC Alpha Pure 2 (420W each)
- Total output: 23.5 kW DC
- 2 rows of 28 panels each
- Arranged in 8 strings of 7 panels (top and bottom rows)
- Strings 1 - 4, west to east
- Strings 5 - 8, west to east.
- Wiring:
- 10 AWG USE-1 from string ends to junction box (~470' each of red and black wire)
- 12 AWG THHN for underground conduit (~65', in 1.25" PVC)
- Terminated in a 12" × 12" × 6" steel junction box with 8x 2-pole 15A, 500V DC breakers (Langir)
- String Integration: Eight PV strings feed two MPPT inputs on each of four inverters inside the container
- A second buried PVC run (~70') was installed to support:
- 48VDC service for a future well pump
- 120VAC service for a water booster pump
2.2 Battery Storage and DC Bus
- Batteries: 12x EG4 LiFePower4 48V V2 (100Ah each)
- Total nominal capacity: 61.44 kWh
- Configuration: Two EG4 steel racks, six batteries each
- Cables: 2x 4 AWG per battery to rack bus rails
- Main DC Bus:
- 600A bus bars (positive and negative), 8-post each
- 4x 4/0 AWG cables (2 positive, 2 negative) from racks to bus bars
- 8x 2/0 AWG cables (4 positive, 4 negative) from bus bars to inverter battery inputs
- Protection:
- 250A fuse inline on each 4/0 positive cable (not yet covered, rear-mounted)
- Expansion Ready: Two additional EG4 LiFePower4 batteries are available for future integration
2.3 Inverters and AC Load Infrastructure
- Inverters: 4x EG4 6000XP (split-phase, 6kW each)
- AC Output Wiring:
- Each inverter terminates at a 2-pole 40A breaker in the load box
- Wiring: 10 AWG THHN, 4-conductor (L1, L2, Neutral, Ground)
- Neutral and ground routed to dedicated bus bars
2.4 Load Distribution Panels
Load Box (Main Distribution Hub):- 4x 40A breakers for inverter outputs
- 2x 100A breakers:
- One feeds the container panel (carport loads, container lighting, HVAC)
- One is reserved for the future residential load center
- Supports lighting, receptacles, and a future 240V mini-split heat pump
2.5 Grounding
- Ground rods installed at:
- PV array structure and PV Junction box
- Equipment container
- Battery racks and inverters
- AC and DC distribution panels
2.6 Inverter and Battery Communication
Inverter Parallel Communication:- Grey RS-485 cables form a closed loop among inverters:
- Right port of inverter 1 →
- Left port of inverter 2 and to 3→
- Right port of inverter 4 →
- Back to left port of inverter 1
- DIP Switch Settings:
- Master (inverter 1): UP/UP
- Intermediates (2, 3): DOWN/DOWN
- Last (inverter 4): UP/UP
- Orange CANbus cable connects inverter P1-R485 port to master battery
- Green RS-485 daisy-chain cables link batteries from port to port
- DIP switches on batteries are configured to assign binary IDs 1–12 per manual
3. Seasonal Performance Estimates
3.1 Projected Daily Output
Season | Sun Hours | Estimated Output | Residential Load | Surplus |
---|---|---|---|---|
Summer (15° tilt) | 6 hrs | 126.9 kWh | 60 kWh | +66.9 kWh |
Winter (45° tilt) | 4 hrs | 84.6 kWh | 60 kWh | +24.6 kWh |
3.2 Interpretation
- Summer: Significant energy surplus, allows room for new loads or more storage
- Winter: System still exceeds average household demand
- Seasonal tilt optimizes solar angle and total yield year-round
3.3 Initial Readings
Initial readings were taken at approximately 6:00 PM on the day the system was powered up:- Battery Voltage: All four inverters displayed a battery input voltage of 51.1 VDC.
- PV Input Voltage: Each inverter reported approximately 320 VDC from its connected MPPT PV inputs, with variation between strings of no more than 3–4 volts.
- There was no AC output measured.
The following day at 10:30 AM, system monitoring showed:
- PV Input Voltage: Consistent with the previous day's measurements (~320 VDC)
- Battery SOC: Increased to 72%, indicating normal charging operation under morning solar conditions.
- Load voltage: 110 VAC
4. Enhancements
4.1 Monitoring and Diagnostics
- Activate inverter logging and web interface
- Tune MPPTs to panel voltage maxima (Vmp ~42V)
- Monitor state-of-charge, voltage symmetry, and BMS alerts
4.2 Load Testing
- Incrementally introduce mission-critical loads
- Confirm load startup surges do not trip inverters
- Verify thermal limits and continuous load capacity
4.3 System Improvements
- Install DC and AC surge protection (SPD Type 2)
- Plan upgrade path from 12 to 10 AWG THHN if voltage drop is excessive
- Add thermal control to container (mini-split)
4.4 Scalability
- Add final two batteries to bring storage to 71.7 kWh
- Add circuits for house loads (HVAC, kitchen, workshop)
- Implement automation for demand control (Home Assistant, Node-RED, Shelly relays, etc.)
5. Construction Notes
Project Timeline (~ Two Weeks)
Friday: The holes for the mounting posts were drilled.
Monday: The posts were set in concrete.Wednesday: The ground mount was framed up and 2 test panels mounted.
Thursday: The 56 panels were mounted to the frame.
By Sunday eve, the batteries were installed in racks, the inverters were mounted on the walls and the cables were set in place for routing and sizing.
During the course of the second week: people were traveling. We purchased overlooked and locally sourced items such as a junction box for the PV wire terminations at the array, PVC pipe (and associated breakers), the AC load box, and the Container/Carport panel.
Saturday: The trenches were dug, cables were bundled.
Sunday: The cables were pulled into PVC, and the trenches were covered.
Monday: The PV wires were terminated, 32 in the PV junction box and 16 into the 4 inverters. The AC Load box was also mounted and wired from each inverter. And finally, the container panel ,meant for provisioning power to the container and other devices in the carport, was wired from the load box. By 6PM we had all systems wired and checked. We powered up the batteries, the inverters and saw 51.1 VDC on each inverter's battery input. We could also see about 320 VDC coming in from the 8 PV strings. However we could not see any voltage on the AC output load side.
After dinner we went out to debug what seemed to be a software configuration problem. By midnight we found the issue to be that we were to plug the master inverter to master battery connection into the CAN bus socket. We plugged a lamp into the Container box outlet and achieved what we called, first-light.
System Completion Highlights:
- 23.5kW PV system online
- 12-battery LFP storage bank live
- All cable runs, protection, and grounding complete
- System ready for real-world load testing