SolarAntics
New Member
Hi y'all,
Getting closer to finishing my designs and could use some guidance. I am building a system for my RV and I unfortunately have not the most ideal components to work with and want to build with what I have. Batteries are miss matched a little, but the ones in series are the exact same. This should be a 24v system. Inverter and chargers are rated at 24v. Please see the diagram
I really don't want to add more bus bars than I need to, but unfortunately the charge controllers will need to be in a separate compartment, so bus bars there. Also, I can't connect the three negative cables from the banks to the shunt, so I figure I need a bar before that. Can confirm?
As far as fuses and breakers go I think I got all that I need. The 120v charger is for emergency generator charging only and is going to be disconnected unless in use (will cut off the MPPT when that is in use manually at breaker). The 120v charger has its own fuses.
Also am wondering about grounding. My understanding is to ground the batteries and the inverter for the AC side. As well as the panels would need grounding, but I think they are all set considering that they are the 400w Renogy solar suitcases (that's why I didn't add a ground there). I need to dig into documentation on that, and possibly a ground is needed at the solar charge controller. Thoughts?
Grounding Plan UPDATE: The manuals are giving me jack squat for answers or no answers at all - - at best they say ground if necessary. I think I should ground the MPPT and AC Charger with 8awg to their own negative bus bar; which goes to the main - and use 4awg to ground the inverter to the main - bus bar and then 4awg from the bus bar to the RV chassis. Logical?
Thank you for all y'alls help!
v5 - Decided to add a kill switch to terminate the batteries since these breakers at each bank likely will not be good enough to act as a cut off (worried about repeated use will eventually wear them to failure - they're cheap with 1/4" lugs so I imagine the rest of components are skimpy too)
(Previous designs in attachments)
v4 - put grounds to bus bars
v3 - added balancers
v2 - made some silly corrections and added data
v1 - lost in the aether
Getting closer to finishing my designs and could use some guidance. I am building a system for my RV and I unfortunately have not the most ideal components to work with and want to build with what I have. Batteries are miss matched a little, but the ones in series are the exact same. This should be a 24v system. Inverter and chargers are rated at 24v. Please see the diagram
I really don't want to add more bus bars than I need to, but unfortunately the charge controllers will need to be in a separate compartment, so bus bars there. Also, I can't connect the three negative cables from the banks to the shunt, so I figure I need a bar before that. Can confirm?
As far as fuses and breakers go I think I got all that I need. The 120v charger is for emergency generator charging only and is going to be disconnected unless in use (will cut off the MPPT when that is in use manually at breaker). The 120v charger has its own fuses.
Also am wondering about grounding. My understanding is to ground the batteries and the inverter for the AC side. As well as the panels would need grounding, but I think they are all set considering that they are the 400w Renogy solar suitcases (that's why I didn't add a ground there). I need to dig into documentation on that, and possibly a ground is needed at the solar charge controller. Thoughts?
Grounding Plan UPDATE: The manuals are giving me jack squat for answers or no answers at all - - at best they say ground if necessary. I think I should ground the MPPT and AC Charger with 8awg to their own negative bus bar; which goes to the main - and use 4awg to ground the inverter to the main - bus bar and then 4awg from the bus bar to the RV chassis. Logical?
Thank you for all y'alls help!
v5 - Decided to add a kill switch to terminate the batteries since these breakers at each bank likely will not be good enough to act as a cut off (worried about repeated use will eventually wear them to failure - they're cheap with 1/4" lugs so I imagine the rest of components are skimpy too)
(Previous designs in attachments)
v4 - put grounds to bus bars
v3 - added balancers
v2 - made some silly corrections and added data
v1 - lost in the aether
Attachments
Last edited: