Feedback and design recommendations on CKT Breaker and wire sizes for my new project
Disclaimers
100 Amp service
Manual Transfer
Position 1-Grid power feeds Main power panel (has no main breaker) that powers the entire home
Position 2- Off House is isolated from the grid
Position 3-Generator
Desired Configuration PNG
Desire is to add a system that can be easily isolated and removed (this is not my forever home)
Grid tied with a battery backup using the following
(2) RUiXU | Lithi2-16 | 51.2V314Ah 16kWh Battery Storage UL1973 ,UL9540A
(2) EG4 6000XP Off-Grid Inverter
Manual Transfer
Position 1-Grid power feeds New Subpanel with 100 Amp main breaker to isolate the entire house from the grid
Add the following Square D - HOM1224L125PC Homeline Load Center 125-Amp
Disclaimers
- I want to add isolations/breakers where I can to make the system easy to install and isolate for easy installation, expansion and removal.
- I plan to add about 10-15KW of solar
100 Amp service
Manual Transfer
Position 1-Grid power feeds Main power panel (has no main breaker) that powers the entire home
Position 2- Off House is isolated from the grid
Position 3-Generator
Desired Configuration PNG
Desire is to add a system that can be easily isolated and removed (this is not my forever home)
Grid tied with a battery backup using the following
(2) RUiXU | Lithi2-16 | 51.2V314Ah 16kWh Battery Storage UL1973 ,UL9540A
(2) EG4 6000XP Off-Grid Inverter
Manual Transfer
Position 1-Grid power feeds New Subpanel with 100 Amp main breaker to isolate the entire house from the grid
Add the following Square D - HOM1224L125PC Homeline Load Center 125-Amp
- 100 Amp breaker to feed the Main Power panel
- 50 Amp breaker to feed primary EG 4 6000XP
- 50 AMP breaker to feed 2nd EG 4 6000XP
- 50 amp Main Breaker that will feed inverter power to the a 50 Amp breaker in the main panel
- 50 Amp breaker from the Inverter 1 Load
- 50 Amp breaker from the inverter 2 load