MrM1
I'm Here, But I'm Not All There
Installing The Big Growatt SPF 12000T 12kw Inverter into a Cargo Trailer for a 12k watt mobile power generator. All the panels will be installed on a pole/post barn and I will connect the Inverter's Solar Charge Controller MPPT to the panels via 8 awg SOOW cable and Anderson Connectors.
First phase of the 11.8kw array pole barn install. Final setup will be the 11.8kw Array. A Growatt 12000T 250vdc input Inverter / Solar Charge Controller. And 2 DIY EVE 280ah 16 cell batteries with BMS.
There are 32 URECO Glory Bifi 370w panels pictured in 8 strings at a total of 189.4 vdc VOC each string. These will go into two 4 in 2 out combiner boxes (from Watts247)
- The first combiner will feed PV1 and PV2 of the Growatt 12kW SPF 12000T DVM MPV Inverter and MPPT Charge Controller 5920 watts from the array
- The second combiner will feed PV1 and PV2 of a Growatt SC48120 MPV 250V PV 120A Charge Controller 5920 watts from the array
I will be installing the Inverter, Charge Controllers, Batteries, and all connections inside a dual axle trailer (the one in the picture below) probably in a week or so.
This set up is for our off grid farm that has no grid power available. We were quoted $37k+ to run power on to the property. I will build this system out for less that $22k. Liking How it is looking so far.
FROM THE MAIN ROAD AND WITH THE TRAILER I WILL BUILD OUT LATER
First phase of the 11.8kw array pole barn install. Final setup will be the 11.8kw Array. A Growatt 12000T 250vdc input Inverter / Solar Charge Controller. And 2 DIY EVE 280ah 16 cell batteries with BMS.
There are 32 URECO Glory Bifi 370w panels pictured in 8 strings at a total of 189.4 vdc VOC each string. These will go into two 4 in 2 out combiner boxes (from Watts247)
- The first combiner will feed PV1 and PV2 of the Growatt 12kW SPF 12000T DVM MPV Inverter and MPPT Charge Controller 5920 watts from the array
- The second combiner will feed PV1 and PV2 of a Growatt SC48120 MPV 250V PV 120A Charge Controller 5920 watts from the array
I will be installing the Inverter, Charge Controllers, Batteries, and all connections inside a dual axle trailer (the one in the picture below) probably in a week or so.
This set up is for our off grid farm that has no grid power available. We were quoted $37k+ to run power on to the property. I will build this system out for less that $22k. Liking How it is looking so far.
FROM THE MAIN ROAD AND WITH THE TRAILER I WILL BUILD OUT LATER
Last edited: