Hi,
Have made some progress with the install!
All equipment mounted, wiring complete, except MPPT to Mini-PDU.
(Waiting on breakers)
All conduit run in the building.
One more run to do, out to the PV array later in the month. 200ft are roughed in, another 50 to finish.
Waiting on delivery of PV panels (12 REC 365 watt), and mounting system (SnapNrack)
When the PV panels are done, will go get the batteries - all day drive to Miami & back to pick up
984 lbs of FLA.
Hope to have this done before hurricane season starts (June)
Have made some progress with the install!
All equipment mounted, wiring complete, except MPPT to Mini-PDU.
(Waiting on breakers)
All conduit run in the building.
One more run to do, out to the PV array later in the month. 200ft are roughed in, another 50 to finish.
Waiting on delivery of PV panels (12 REC 365 watt), and mounting system (SnapNrack)
When the PV panels are done, will go get the batteries - all day drive to Miami & back to pick up
984 lbs of FLA.
Hope to have this done before hurricane season starts (June)