John Schmidt
New Member
- Joined
- Dec 30, 2020
- Messages
- 82
Hi all! New to the forum. We spent a good part of the covid summer installing a 9.6kW array with 24 panels. 2 strings of 12. I finally have 12 volts at each string coming into the SolarEdge inverter from the SolarEdge optimizers. Looks ready for commissioning. However, the power company has not installed the net metering meter yet. If I throw the 50 Amp dual pole breaker on the main panel to feed the power to the inverter for commissioning, I assume that the inverter will start powering the grid after the optimizer/inverter pairing process is complete (correct??). I don't know. I know with my manual start backup generator, I need to make sure that I don't back feed the grid. The inverter has auto-protection to not feed the grid when the grid is down, but are there any issues with running the inverter without the net metering meter? I'd like to get it ready for the net metering meter, if at all possible. Granted, I'd be generating power and not getting any payback for it, but will it subtract at all from what I am using during the day when it is sunny? I read on one forum that said without a net-metering meter, the old meter would still record the current as it does now, and not subtract from what I generate. Thoughts? Thank-you in advance!