Stupid Monkey
New Member
- Joined
- Dec 14, 2019
- Messages
- 193
So finally got my BLS Cells - 24pc of 150ah and I've started the top balance.
Cells ship at 65% charge right? so each cell needs ~50ahhr of charge, 24 cells, 1200ah
i've a 10A charger, but raising 3.3 - 3.4V its started at 1A, so by the time that stage drops to 0A assume average 0.5A at every stage (3.4-3.5 next stage etc) thats 2400hrs, or 100 days .....
Have I calculated wrong? What would you do ?
Cells ship at 65% charge right? so each cell needs ~50ahhr of charge, 24 cells, 1200ah
i've a 10A charger, but raising 3.3 - 3.4V its started at 1A, so by the time that stage drops to 0A assume average 0.5A at every stage (3.4-3.5 next stage etc) thats 2400hrs, or 100 days .....
Have I calculated wrong? What would you do ?