Hey All,
I currently have a grid-connected PV system with APSystems DS3 inverters. I'm interested in adding batteries primarily to save on TOU rates, but secondarily to provide backup power for some critical loads. The goals for my battery system are:
1. Offset peak electricity usage by discharging the batteries to supply my local loads (load both "downstream" in a critical loads panel, and "upstream" in my main panel, assuming the grid is operating normally).
a. When my PV system is meeting the demand/exceeding the demand and exporting power to the grid, the batteries would not discharge.
b. When I'm a net consumer from the grid (PV not meeting/exceeding demand), discharge the batteries to approximately offset whatever power I'm currently using.
2. Provide backup power to a critical loads panel in case of a grid outage, ideally with AC coupling my existing APSystems PV setup.
I've identified the Conext XW Pro 6.8kW as a possible solution to meet these needs, but even after reading all installation/configuration/whitepapers I could find on it, I'm unclear if it will actually meet my needs. Considering the architecture outlined in the figure below (with appropriate current monitoring in the main panel provided probably by a WattNode):
Can I configure the XW Pro to try to "zero" the power input from the grid during peak hours, by using the batteries to backfeed power to AC1 (obviously only in cases where the grid is operational, since backfeeding AC1 would not be allowable if the grid was down)?
If this is not possible, is anyone aware of an inverter/charger that might meet my needs? I think some of the newer EG4 stuff would probably work, but I'd like to not have to buy something with solar input, if possible, since I have no use for a DC string inverter function.
Thanks for any and all advice!

EDIT: To better clarify my concerns, I can't tell from the documentation whether it's even possible to backfeed AC power sourced from the batteries in this configuration. If it is possible, it's not clear if there's any way to regulate the inverter so that the backfed current is approximately matched to the grid demand (note that in this application, error in matching the grid demand exactly is acceptable - I can backfeed or import from the grid a lttle bit. I'm just trying to minimize my peak time usage).
I currently have a grid-connected PV system with APSystems DS3 inverters. I'm interested in adding batteries primarily to save on TOU rates, but secondarily to provide backup power for some critical loads. The goals for my battery system are:
1. Offset peak electricity usage by discharging the batteries to supply my local loads (load both "downstream" in a critical loads panel, and "upstream" in my main panel, assuming the grid is operating normally).
a. When my PV system is meeting the demand/exceeding the demand and exporting power to the grid, the batteries would not discharge.
b. When I'm a net consumer from the grid (PV not meeting/exceeding demand), discharge the batteries to approximately offset whatever power I'm currently using.
2. Provide backup power to a critical loads panel in case of a grid outage, ideally with AC coupling my existing APSystems PV setup.
I've identified the Conext XW Pro 6.8kW as a possible solution to meet these needs, but even after reading all installation/configuration/whitepapers I could find on it, I'm unclear if it will actually meet my needs. Considering the architecture outlined in the figure below (with appropriate current monitoring in the main panel provided probably by a WattNode):
Can I configure the XW Pro to try to "zero" the power input from the grid during peak hours, by using the batteries to backfeed power to AC1 (obviously only in cases where the grid is operational, since backfeeding AC1 would not be allowable if the grid was down)?
If this is not possible, is anyone aware of an inverter/charger that might meet my needs? I think some of the newer EG4 stuff would probably work, but I'd like to not have to buy something with solar input, if possible, since I have no use for a DC string inverter function.
Thanks for any and all advice!

EDIT: To better clarify my concerns, I can't tell from the documentation whether it's even possible to backfeed AC power sourced from the batteries in this configuration. If it is possible, it's not clear if there's any way to regulate the inverter so that the backfed current is approximately matched to the grid demand (note that in this application, error in matching the grid demand exactly is acceptable - I can backfeed or import from the grid a lttle bit. I'm just trying to minimize my peak time usage).
Last edited: