Going to post updates here hopefully someone will find it useful.
X100 Q-Cell peak Duo 325 panels paired with enphase IQ7+ inverters.
Ironridge ground mount 3in.
Finally getting to mount some panels. Opted to only install the first half of rails case I had an unforeseen issue. 4th and 5th rows need a second person for sure to get them up and in position. Tell this point I’ve been able to do everything on my own with the bobcat.
Well this project is a wrap! Got my final yesterday . Here’s a few pics of how I did the electrical. All in all it was a good experience and hopefully it has many years of life. 5 months to build working on it a couple hours a day.
Money saved doing it DIY?
Quotes I got for this system ranged...
I agree, the plans don’t call for any but I do have sole poles I plan on adding that are just lying around. I’ll probably just do the ends E-W and N-S and the middle area for some added support..