I had to do over 40 hours of Enphase online training to become certified to commission my own system. It does need to be provisioned and commissioned. I tried to do it without being certified and just online tech support. It’s not something they can do over the air even though they tried. If it...
I just added some panels and a couple of batteries. So I don’t have good numbers. But for June (month to date). I have consumed 1.1MWh. Produced 1.2 MWh, imported 540kWh, exported 598kWh, charged 108.9 kWH, discharged 90 kWh. My Batteries have been commissioned the last 12/11 days and are set at...
Background and current system.
I have 25 panels with IQ8 inverters 10KWh
IQ Combiner 4c
IQ system controller 2
2-3T Enphase batteries (just installed, I got certified and installed them)
All my solar wiring is on the north side of my home.
L1 & L2 from the battery terminals on my controller go...
I did read somewhere on the form how someone used a pc board device to add an inverter. I would be interested in something like that if it works and an option.