I had to change my option for inverter as the one I went after is OOS due to supply shortages. I went with a Growatt 10K grid tie (meets all the requirements for my energy supplier). This has 4 MPPT's that support two strings each.
My question is: does the 600V limit apply to the entire unit, or is that PER MPPT?