diy solar

diy solar

Most reacted posts

  • Post in thread: BMS in Series for Failsafe - Possible?

    My naturally cautious nature leads me to ponder BMS failures because they are critical to any LiFePO4 battery build and are a single point of failure. AFAIK Mosfet based BMS may/could fail with the Mosfets stuck in a charge or discharge state thereby leading to unpleasant outcomes. Is this...
  • Post in thread: Multiplus II Bypass Switch

    So something like this: With this wiring: And these steps to enable Bypass: The benefit of the Load Connect Switch separate from the Bypass Switches is that in the event of Grid failure, the Multiplus II will disconnect AC2 Out but it gives me the choice based on expected PV and battery SOC...
  • Post in thread: Erratic & Erroneous Cell Voltages Whilst Charging - JKBMS B2A24S15P

    JKBMS B2A24S15P Readings for Cell 9 in the attached video are the culprit. Whilst charging with above 35 amps to 55.2v (3.45v/cell), the voltage is 'reported' to be widely fluctuating. Other cells also fluctuate but not to the same degree. 'Reported' because 2 different multi-meters across...
  • Post in thread: 420mV Voltage Drop across JK BMS - SOLVED

    There is no load - not yet connected to Inverter/Charger. BMS is cool (about 24C). BMS is turned on. When turned off, I wouldn't expect to get any readings across the BMS.
  • Post in thread: Grid Tie Victron ESS with DIY LiFePO4 Battery in Australia - Regulatory Issues?

    Ghosty - what did your 'chap' (the mate of a mate :)) advise?
  • Post in thread: Grid Tie Victron ESS with DIY LiFePO4 Battery in Australia - Regulatory Issues?

    I have managed to at least get a quote for the installation that includes inspector approving. However, after me having agreed to go ahead with the quote, sparky has gone quiet for a few days. :(
  • Post in thread: Grid Tie Victron ESS with DIY LiFePO4 Battery in Australia - Regulatory Issues?

    Let us all know how it goes.
  • Post in thread: DDP China to Australia with Shenzhen Qishou Technology (Cassie Wang)

    Have requested a DDP (Delivered Duty Paid) quotation from Cassie Wang at Shenzhen Qishou Technology via Alibaba messenger. This is the quote. 16 pieces EVE LF280K total price -- USD 1648 Shipping cost - - USD 390 Transportation mode - - DDP Shipping time - - 55-65 days DDP to Australia Total...
  • Post in thread: Erratic & Erroneous Cell Voltages Whilst Charging - JKBMS B2A24S15P

    I am fairly sure the BMS would throw a tantrum with that. It is expecting 16 cells in sequence 1-16.
  • Post in thread: Erratic & Erroneous Cell Voltages Whilst Charging - JKBMS B2A24S15P

    Is the reason for this statement that Cell 9 voltage is calculated by the BMS using measurement points on Cell 8 +ve terminal & Cell9 +ve terminal? Why would the reported voltage be erratic if they were not the same resistance/conductivity? I could understand it if the voltage was consistently...
  • Post in thread: Multiplus II Bypass Switch

    I did ask a Licensed Electrical Inspector about switching the Neutral downstream of the MEN link & he said it was OK provided continuity with the MEN link was maintained. In the Victron VE Config software, I would be selecting the Grid Code 'Australia A - No N-Bypass' which maintains continuity...