Hi,
I have been looking at some threads, but didn't find my exact situation.i have a Sol Ark 15kW inverter that I am planning on connecting to a critical load subpanel. My main panel is a combo meter/main 200A: see photo. The meter is attached directly to the 200A disconnect.
Can I install...
Hi,
I have a grid-tie ~10kW (24x 400W + 24x Enphase IQ8M) system.
I am interested in adding battery backup. I want to add 44kWh LiFePO4 batteries. I am looking for inverter/charger suggestions that will AC couple with the Enphase micros.
Any inverter suggestions? I am looking at the...
The datasheet mentions something about fast swapping with a busbar connection. Not sure what this means. Could do something like 600A busbar->ring terminal->4/0 wire->Anderson terminal->Anderson PP180->battery?
Hi,
I have 4x 11kWh 48V battery modules. I would like to setup a bus bar to run them in parallel. I also plan to use Anderson PP180 style connectors. Any recommendations for 600A bus bar that will fit these connectors?
Thanks!
Hi,
I am planning on going Solar in 2 phases.
Phase 1: Add battery backup (48V, 44kWh LifePO4+Seplos BMS modules), Inverter/Charger and power a critical load subpanel.
Phase 2: Add solar (7-10kW) + MPPT controller(s).
Option 1/Phase 1: I would like the inverter to prioritize grid for...
Hi,
I am located in San Jose, CA. I am working on building a battery backup system. I have 44kWh 48V LifePO4 batteries with Seplos BMS.
I have a 100A subpanel handling critical loads that is currently utility powered. Max power from that panel is ~3kW @ 120V ~= 30A. No 240 yet... In phase...