If I'm stacking 4 Mason Boxes, can I use the 25mm2 cable or I should only use the 50mm2?
Secondly Is it advisable to go straight from battery box to busbar instead of parallel the battery boxes to each. Someone told me he doesn't think I should parallel my battery boxes with the parallel...
Hi.
I wanted to know, this particular Mason Box Seplos is selling, were you the one who designed it or pitched it to them? Did you have any role in it's development? Just curious
Hi. What percentage of your 60kw do you use daily? Are you off grid? Do you have air conditioning?
Sorry I'm asking because I'm just trying to set up my solar and even though 30kw is what I planned to do, but I'm thinking of just doing 60kw once and for all instead of having to think of...
Hello. Some help needed here please. Seplos BMS seems to be seeing my cell capacity as 200Ah even though I used CATL 302Ah cells. Is it a setting in the BMS or what do I do to see full capacity.
I have 4 Seplos boxes stacked in parallel and these are their current state. Should the differences in SOC be this much? Isn't the variance too much? What should be done to correct this?
Guys, I'll like to know, did you guys receive this Power Cable (2m) and Parallel Cable (50mm) with your Boxes?
Seplos is asking me to pay an extra $71 and $51 respectively for the power cable and parallel cable??
Does anyone know if I can use this for the CATL 302AH cells also?
The EVE is 175*72*205 mm
The CATL is 207*72 * 174mm
The pole of the CATL is 11mm, and the height after welding the stud is 218mm.
Do you think it'll fit well in the Mason 280 box?
If i decide to use busbars and do something like this. Does that mean I won't be using any parallel cables at all. Instead, more inverter cables? (longer it seems). Sorry for many questions, I'm a newbie. Just learning along the way
Yes they were. They were assembled in China. Seplos shipped the box to my cell supplier who did the top balance, assembled them and shipped the packs to me.
Seplos just replied my message now. Do you think it's best to set it manually or just allow the BMS get the real capacity through full charge and discharge?
Also, if I'm discharging, do I discharge to 0%? Considering there is Low SOC parameters.