Huckleberry
New Member
I'm interested in configuring this up for battery-less operation temporarily. Due to a shipping mix-up the batteries didn't get delivered before I left to the cabin, and I won't be back for 2 weeks.
Per this video from EG4:
It sounds like this is possible. I have 6kw of solar panels installed in full sun on a ridge, and I'm just looking to run a 1900W load (AC with soft start). If I have to restart the invertor a few times, it wouldn't be the end of the world, but I can't find any information on doing this in the manual, as I read it.
Suggestions?
Per this video from EG4:
It sounds like this is possible. I have 6kw of solar panels installed in full sun on a ridge, and I'm just looking to run a 1900W load (AC with soft start). If I have to restart the invertor a few times, it wouldn't be the end of the world, but I can't find any information on doing this in the manual, as I read it.
Suggestions?