Hi, I have growatt all in one inverters. I hooked up all my panels in parallel (couldn't serialize them due to max open circuit limit on growatt boxes). (3000TL LVM)
One of my growatt boxes came DOA and another just broke so i'm down to using 4 in split phase. I'm planning to upgrade to the eg4 inverter boxes that's sealed and has a 10 year warrantee.(EG4 18KPV)
All my solar panel strings are grouped in parallel with 5 panels each. I was wondering if there is anything wrong with serializing the 5 panel strings together to hook into the eg4 inverter boxes? Having my panels parallel before a serialize since I already have the wiring down, it would just be less effort for me.
One of my growatt boxes came DOA and another just broke so i'm down to using 4 in split phase. I'm planning to upgrade to the eg4 inverter boxes that's sealed and has a 10 year warrantee.(EG4 18KPV)
All my solar panel strings are grouped in parallel with 5 panels each. I was wondering if there is anything wrong with serializing the 5 panel strings together to hook into the eg4 inverter boxes? Having my panels parallel before a serialize since I already have the wiring down, it would just be less effort for me.