sjordan0228
New Member
Been going back and forth on this. I found a video online where someone wired there 18kpv like this. He is grid tied and sells back to the electric company. This passed inspection. This setup seems to be just like the diagram in the 18k manual for "Whole Home backup with Supply side tap". However he is using extra lugs on the bottom of the 200A Fused Service Disconnect to send power to the 18K and the Transfer switch (side tap in the 200A Service disconnect instead of in the meter). Also the "PV Interactive System 2-Pole Fused Disconnect" is missing. I am assuming here is that the 200A AC Fused Service Disconnect is handling this. Is this a bad idea? My current setup (no solar) is just my meter going directly into my main panel which has a 225A
![1716653412348.png 1716653412348.png](https://diysolarforum.com/data/attachments/217/217567-9c95c67bc297b09f081160c222fbdc20.jpg)
![1716653412348.png 1716653412348.png](https://diysolarforum.com/data/attachments/217/217567-9c95c67bc297b09f081160c222fbdc20.jpg)