MikeSpeegle
New Member
Thank you so much all I need is the shutdown part for pytes and I am gonna order 16 and figure out which stack or cabinet I need for inside my garage. I’m ready to order today.I'm looking into this! Please stand by and I'll see what we can do.
By the way, you don't need the 18k inverter to use the shunt trip. Two pins of the communication cable are what triggers it - I'm not sure if they need voltage applied on these pins or just connected off the top of my head. I recall pin 3 & 8. That said, since Pytes is UL9540 with Sol-Ark that would be the better choice for this application, because the AHJ could require UL9540 in the future.
Thank you again. This place is always been the place where I can find answers that are real. I appreciate everybody that participates here. I would’ve given up long time ago without this place.