I have a 13kW Sunpower/Sunvault install and was recently granted PTO by Edison. My installer is not answering my calls and emails, which is typical of my experience with them, and I would like to turn the system on.
The breakers for solar, ESS inverter/PVS6, and ESS grid sense are all off. The Sunvault has two breakers beneath a small access panel on the right side, with the left one off and the right on. I have the hub connected to my home network via ethernet, and it has an IP address, but the Sunpower app is not able to find my system when I attempt to set that up.
I'm assuming that I can just turn these on, which would presumably result in production, but I'm apprehensive about making assumptions with something like this, especially with a battery involved, and was hoping someone here might provide some guidance. Apologies if this is a bit outside the scope of the forum, as this is technically pretty late stage DIY.
The breakers for solar, ESS inverter/PVS6, and ESS grid sense are all off. The Sunvault has two breakers beneath a small access panel on the right side, with the left one off and the right on. I have the hub connected to my home network via ethernet, and it has an IP address, but the Sunpower app is not able to find my system when I attempt to set that up.
I'm assuming that I can just turn these on, which would presumably result in production, but I'm apprehensive about making assumptions with something like this, especially with a battery involved, and was hoping someone here might provide some guidance. Apologies if this is a bit outside the scope of the forum, as this is technically pretty late stage DIY.