i have 1.4kw 10yr old "leased" PV on my roof. i am under contract with an external contractor for a new 8.4kw PV system (Enphase). they are planning to submit this SLD for NEM2.0 with PG&E (bay area).
please review my SLD for below questions i have.
1- my current main breaker and service are 100amp. any ways i can avoid MPU?
2- should i ask to change anything to ensure that it is easy to add battery system later?
3- i have an EV already. in this SLD, where will my 32amp EV charger be connected?
4- in this SLD, is box F unnecessary? can't the 60A breaker in box E be used to disconnect the PV going into main panel G?
please review my SLD for below questions i have.
1- my current main breaker and service are 100amp. any ways i can avoid MPU?
2- should i ask to change anything to ensure that it is easy to add battery system later?
3- i have an EV already. in this SLD, where will my 32amp EV charger be connected?
4- in this SLD, is box F unnecessary? can't the 60A breaker in box E be used to disconnect the PV going into main panel G?