Here is my setup thus far.
Four 300 watt panels - 2s2p. ->
20 amp switch (near controller) ->
controller ->
7.68 kWh battery bank 24v ->
100a breaker (near positive battery terminal)—>
24v 2000 watt Samlex inverter
also will have 100a shunt near negative battery terminal for the battery monitor
Am I missing any fuses or breakers?
I will ground the panels with a grounding rod. Do I need to ground the inverter as well?
edit
The controller and inverter will be in my garage. Can I ground them by running a cable to an outlet (Thus using the house ground)?
Four 300 watt panels - 2s2p. ->
20 amp switch (near controller) ->
controller ->
7.68 kWh battery bank 24v ->
100a breaker (near positive battery terminal)—>
24v 2000 watt Samlex inverter
also will have 100a shunt near negative battery terminal for the battery monitor
Am I missing any fuses or breakers?
I will ground the panels with a grounding rod. Do I need to ground the inverter as well?
edit
The controller and inverter will be in my garage. Can I ground them by running a cable to an outlet (Thus using the house ground)?
Last edited: