G.W. Mad Scientist
New Member
This week I entered phase 2 of my solar project (upgrade the breaker box with additional Breakers, interlock panel, and wire power room transfer panel to the breaker box)phase one (to complete my power room which is about 95% completed).
I started by removing the old breaker box cover and staring at this thing for a long time figuring out how to get the power into the box through the Attic in the least invasive way. Also at the start of this the old breaker box had three extra 120 spaces. I needed to add two new 240 Breakers. One 60 amp for the generator input and one 60 amp for power out.
After going into the attic and staring at it there was so many wires coming out of the top of the breaker box into the Attic. As well as it appeared that I had a double plate(later turn out to be 3 2×4's thick)on that wall above the breaker box which further was going to make it more difficult.
So I then decided I was going to have to come in next to the breaker box on the outside of that wall stud and bring it through the stud into the top of the breaker box as much as I hated to do it I cut panel of sheetrock out above the breaker box.
This also will allow me access to the top of the box one more time to run a 60 amp feed from the newly installed additional 240 breaker. It run through my attic to the side of my house which will later feed my garage and power my mother's air conditioners with the grid tie system once it's installed.
I started by removing the old breaker box cover and staring at this thing for a long time figuring out how to get the power into the box through the Attic in the least invasive way. Also at the start of this the old breaker box had three extra 120 spaces. I needed to add two new 240 Breakers. One 60 amp for the generator input and one 60 amp for power out.
After going into the attic and staring at it there was so many wires coming out of the top of the breaker box into the Attic. As well as it appeared that I had a double plate(later turn out to be 3 2×4's thick)on that wall above the breaker box which further was going to make it more difficult.
So I then decided I was going to have to come in next to the breaker box on the outside of that wall stud and bring it through the stud into the top of the breaker box as much as I hated to do it I cut panel of sheetrock out above the breaker box.
This also will allow me access to the top of the box one more time to run a 60 amp feed from the newly installed additional 240 breaker. It run through my attic to the side of my house which will later feed my garage and power my mother's air conditioners with the grid tie system once it's installed.
Attachments
Last edited: