BackyardBandit
New Member
The intent here is to use transfer switch in the event of grid failure to power main panel through the load side of the Sol-Ark 12k from battery/PV... normal grid-tied operation otherwise.
Homeowner is aware they will have to manually shed loads in the main panel before activating bypass switch. Space in closet where MSP is located is limited so they don't want PLP.
Found a diagram for the 15k with a SLD like this one, but not for the 12k. Think it will work?
Rough SLD attached.
Homeowner is aware they will have to manually shed loads in the main panel before activating bypass switch. Space in closet where MSP is located is limited so they don't want PLP.
Found a diagram for the 15k with a SLD like this one, but not for the 12k. Think it will work?
Rough SLD attached.