I submitted my plans to the city and they said I needed to show a PV production meter. My plan man came up with what's below. The city guy responded with "The PV meter will need to be after the AC disconnect and main panel. Currently it is after the main meter on the one line.
I don't understand what he wants me to do. Does anyone here know? Thanks