My county in Illinois had a checklist of required submittals when you applied. Best way to make it go smoothly is follow their requirements.I am submitting my plans to Clark County Nevada. Any advice on making the permit process go smoothly?
Don't have any advice, but did want to welcome you to the forums and congratulate you on going solar!
Hope to hear about your system & setup!
Thanks Mike. Appreciate the guidance. I did find a checklist but the process is way more simple than I thought. I submitted plans through the City website. Pay the fee. Install and get final approval.My county in Illinois had a checklist of required submittals when you applied. Best way to make it go smoothly is follow their requirements.
Thanks Mike. Appreciate the guidance. I did find a checklist but the process is way more simple than I thought. I submitted plans through the City website. Pay the fee. Install and get final approval.
Thanks Svetz. My permit process went smoothly. Unfortunately, I think I stepped on a bear trap by ordering my solar panels from Solaris. I placed my order with an expected ship date of May 25. As soon as I placed my order the date changed to September. Now I can’t get any answer from them. I will be disputing the charge on my credit card. I didn’t realize they had a questionable reputation.Don't have any advice, but did want to welcome you to the forums and congratulate you on going solar!
Hope to hear about your system & setup!
I used a company called CED greentech. They have locations in Las Vegas, and Reno. They are a sister company to CED electric that is a large wholesale electric supplier. Brick and mortar building you can walk into, not like some of the online vendors.Thanks Svetz. My permit process went smoothly. Unfortunately, I think I stepped on a bear trap by ordering my solar panels from Solaris. I placed my order with an expected ship date of May 25. As soon as I placed my order the date changed to September. Now I can’t get any answer from them. I will be disputing the charge on my credit card. I didn’t realize they had a questionable reputation.
Doesn’t make sense not to have 240. How will you run HVAC? I submitted plans to City of Henderson NV and was issued a permit for the 2 LV6548 to make 240V system.I'm building in Lyon county and asked my electrical contractor to pre-run conduit for solar power to the inverter. He told me that it is not permissible in NV Energy-ville to have a 240 volt solar system. I think he's wrong. Anyone here have any experience with that -- either as a backup power source or hybrid grid tie source?
Also any help with the permitting process? One line diagrams and spec sheets or ??? (particularly for hybrid-grid-tie)
Thanks in advance.
Gotcha. Doesn't make any sense to me either. I'll check on my neighbor's install. It charges a Tesla and must be 220-240VDoesn’t make sense not to have 240. How will you run HVAC? I submitted plans to City of Henderson NV and was issued a permit for the 2 LV6548 to make 240V system.
Good to know. Sorry you had to have that experience.. I didn’t realize they had a questionable reputation.
How did the permitting process go? Everything work out ok?Thanks Mike. Appreciate the guidance. I did find a checklist but the process is way more simple than I thought. I submitted plans through the City website. Pay the fee. Install and get final approval.
Was it clear before mounting that you have special rules? Pretty sure IRC says that 36” default spacing can be waived in a couple ways.Aside from the permitting process is the fire inspection. Big concern was batteries separated by 36”. Some manufacturers say 6”, but the fire department holds fast to 36”
I am having the contractor do the install. It seems that 36” can get waived.Was it clear before mounting that you have special rules? Pretty sure IRC says that 36” default spacing can be waived in a couple ways.
That’s the problem they ran into. There was not enough wall space to do the 36”. I don’t know if they were talking to the other fire dept before their install or were reacting to a red rag failed inspection.However, it would be extremely terrible if there was not enough space to simultaneously satisfy 36" and battery setback from building penetrations into habitable space
I’m not the right guy to ask, but it seems to me from what I saw today the permitting and fire inspection are two different entities. There is also the utility inspection.OK, I guess it doesn't really matter if you do things the right way and get the permits before starting work.
That’s the problem they ran into. There was not enough wall space to do the 36”. I don’t know if they were talking to the other fire dept before their install or were reacting to a red rag failed inspection.
I’m not the right guy to ask, but it seems to me from what I saw today the permitting and fire inspection are two different entities. There is also the utility inspection.
Three different entities are involved, so it’s more than the permitting.
1) permit is approved by the town
2) install happens
3) Fire inspector checks install (this happened today)
4) Town inspects install ( tomorrow)
5) Power company comes out and approves system (several weeks)
6) Backup circuits are wired and system goes live. (Day after power company arrives).
Since the contractor handles everything for an install, your list is certainly more correct than mine.My town does it this way, so in principle it would have been caught at step (2)
1) Permit approved by town
2) Permit approved by fire district
3) Town inspection
4) Fire district inspection
5) Send proof documenting that you passed (3) and (4) to POCO (no inspection on their side needed)
6) POCO issues PTO and you can turn on the inverter
For DIY solar I waited until both (1) and (2) approved permits before placing hard order for equipment.
When I DIY my ESS, you'll bet I'm going to call up the fire district and town to confirm that they checked the spacing and vehicle protection and all that other PITA crap that is annoying to fix if it's wrong. Before I order any batteries, let alone mount them.